05-04-2024

Below are all the Glanmire Flood Relief Scheme Updates for 05-04-2024.

Good morning,

I am contacting you with an update on the next phase of works for the Glashaboy Flood Relief Scheme.

I have attached details of overnight works which will commence on Monday night from 7pm until 7am approx..

Also, here are the latest updates for the traffic management in the following areas:

Hazelwood Road/R639

  • Stop/Go will be in place from 7am – 7pm with traffic lights from 7pm – 7am
  • Commencing on Monday 8th April

New Line/Brooklodge East

  • Stop/Go will be in place from 7am – 7pm with traffic lights from 7pm – 7am

Copper Valley Vue

  • Work will continue within Copper Valley Vue, with internal traffic management
  • Commencing on Monday 8th April

Sallybrook Industrial Est

  • Traffic management is suspended at present

Bleach Hill/Cúil Chluthair

  • Temporary Traffic Management will be in place on Monday/Tuesday/Wednesday 8th– 10th while reinstatement work is carried out.

Sorensen would like to take this opportunity to thank all the local residents and stakeholders for their continued patience while the works are progressing.

If you believe that this information may be beneficial to others in your network or community, please feel free to circulate this email accordingly. We understand the importance of keeping all stakeholders informed and engaged throughout this process.

Should you have any questions about this closure, or the works being carried out for the Glashaboy Flood Relief project, please do not hesitate to contact me directly at 086 032 6171.

Thank you for your attention to this matter, and your assistance in ensuring the successful completion of this project.

Kind regards,

Elaine Cronin

Sorensen Liaison Officer